Mid-Western Watermain Upgrade

Client
Mid-Western Regional Council
Location
Gulgong, NSW
PROJECT OVERVIEW

Trazlbat delivered the renewal of ageing water supply infrastructure in Gulgong, improving the reliability, performance, and quality of potable water services for the local community. The project involved the replacement of existing water mains along Bligh Street and Prince Street, providing a modern and resilient water distribution network designed to support future demand and reduce maintenance requirements.

Delivered under a lump sum contract arrangement, the works included the installation of new PVC water mains, associated network infrastructure, service connections, testing, and commissioning.

Scope of Works

  • Installation of approximately 500 metres of DN100 PVC potable water main.
  • Supply and installation of associated hydrants, valves, and water network fittings.
  • Construction and transfer of property service connections to the new water main.
  • Excavation, bedding, pipe laying, jointing, backfilling, and compaction works.
  • Live connections and integration of the new infrastructure into the existing water supply network.
  • Pressure testing, flushing, disinfection, and commissioning of the completed water main.
  • Reinstatement of roads, footpaths, and all disturbed areas following construction.
  • Provision of all labour, plant, materials, traffic management, and ancillary works required for project completion.

Project Challenges

  • Identifying and managing existing underground utility services within a constrained urban environment.
  • Addressing unknown locations and conditions of ageing underground infrastructure encountered during construction.
  • Safely integrating the new water main into the live potable water network while maintaining service continuity.
  • Minimising disruption to residents, businesses, and road users throughout the construction period.
  • Maintaining safe work zones and effective traffic management within residential streets.
  • Coordinating stakeholder communication and service changeovers to reduce community impacts.

More Recent Work

Several colorful utility pipes—orange, white, blue, and black—are laid in a deep trench at a construction site, with an excavator and trees visible in the background under a cloudy sky.

Utilities Package for Western Harbour Tunnel

Aerial view of a rural area with a newly paved curved road, houses, trees, and green fields under a blue sky with scattered clouds. The landscape is surrounded by gently rolling hills.

Nanima Village Civil Works